Monday 23rd September 2019

Planned 'UPS maintenance SmartDC, scheduled 3 weeks ago

On the 25th of Septemeber 2019 SmartDC, the datacenter in which our servers are located, will perform a UPS maintenance for replacing the UPS in the powerhouse. During this replacement they will perform a switchover at 08:00 CEST.

Maintenance start: 25/09/2019 07:00 CET Maintenance end: 25/09/2018 11:00 CET Expected impact: This maintenance should not affect the availability of services as the generators run NET - PARALLEL. No power failure should occur, a strict protocol has been drawn up for this which excludes all risks step by step.

During the maintenance, our support staff as SmartDC will be available to answer e-mails sent to support@snel.com.